Work on NG5 and NG6 is now complete under the St Francis Bay Long Term Coastal Protection Scheme. The focus remains on completing NG1 and progressing with construction at NG3 ahead of the festive season shutdown.
NG5 And NG6 Complete
Maintenance armouring on NG5 and NG6 has been completed. Both groynes are now finished in accordance with the project plan.
NG1 Nears Completion
NG1 is expected to be completed within the next week or so, once the remaining capping work is finished. This involves filling and completing the access onto the groyne.
The construction team will then return to NG3 at Peter Crescent, where a further 6,000 tonnes of armour rock are scheduled to be placed before the festive season shutdown.
Beach Nourishment at Anne Avenue

Beach nourishment has moved to Anne Avenue, where sand is building up steadily on the southern side of groyne NG1. The outflow pipe will continue delivering sand along Main Beach until work pauses for the summer holidays.
Road Rehabilitation Begins On Week Starting 9 November
The appointed contractor will begin rehabilitation work on Aldabara Run, Poivre Crescent and Grand Comoro during the week starting Monday, 9 November. The work is scheduled for completion by 30 November.
Save The Date — SFPO Annual General Meetings
Both meetings will take place at St Francis Links on Thursday, 10 December 2026:
SFPO Association AGM: 15:00 – 16:00
SFPO NPC AGM: 16:30 – 17:30
A YouTube feed of the SFPO NPC AGM will be available through the St Francis Property Owners website.
Stay Informed
Further details, updates and progress reports can be found on the St Francis Property Owners website under the NEWS header.
SFPO NPC Contact:
Lyn Aitken – Administration Manager
Phone: 042 294 0594
Email: info@sfpo.co.za
Office address: 9 Philippa Place, St Francis Bay
–