Dredging Pipe Placement Update

Dredging Pipe Placement Update

The first 360 meters of the dredging pipe have been placed, heading downstream along the Kromme River from the Sand River Delta.

As per the diagram, the pipe sections to the right of the diagram and marked in Red are lying on the sand bank, the pipe sections marked in Green will be sunken under the channel, and the following sections, in Red, lead towards The Cove.

The next sections of the dredging pipe to be placed will head further downstream and towards The Cove.

Stay Informed

Further details, updates, and progress reports are available on the St Francis Property Owners Association website under the SFPO NPC (SRA) menu.